Small modular reactors: going round in circles

Materials World magazine
,
2 Sep 2014

The days of large nuclear power plants could be numbered, especially in countries with a marketfocused approach to energy. Tim Probert explores the development of small modular reactors, including Urenco’s efforts in the UK.

The evolution of civil nuclear power in the past 60 years can be boiled down to one key change. Small submarine reactors were re-purposed to produce electricity for the grid and scaled up on an ever-larger basis. From the original submarine reactors of around 50MWe, civil nuclear reactors are now commonly of a size greater than 1000MW.

French vendor Areva’s European pressurised water reactor (EPR), which will be used at Hinkley Point C in Somerset, is a 1,650MWe unit. However, at £8bln each, the EPR is a phenomenally expensive product. The increasingly large reactors and associated safety structure and systems are, some argue, examples of diseconomies of scale – the larger the reactor, the less competitive it becomes. Led by the USA, there is now a concerted effort to explore what are called small modular reactors (SMRs) to make nuclear more competitive with other forms of power generation, such as gas and coal. Defined by the International Atomic Energy Agency (IAEA) as under 300MWe, SMRs fall into two general categories – miniature versions of their larger brothers, designed to be mass-produced and bolted together to form a large power plant, and small reactors designed to be deployed for embedded generation for industrial use.

Most of the SMR designs are a reversion to the initial, submarine-scale pressurised water reactors. Oregon-based NuScale Power, with the backing of its primary investors Fluor Corp and Rolls-Royce, is developing a 45MWe modular reactor that can be scaled up to 12 units.

The reactor modules measure 20m high and 2.7m in diameter, and sit within a containment vessel. Each module, weighing 650 tonnes, is self-contained and operates independently, although all can be managed from a single control room. American engineering company Babcock and Wilcox’s mPower is a similar SMR concept, albeit much larger. The 180MWe reactor measures 23m high and 4.5m in diameter, and features an integral steam generator derived from marine designs as well as 69 conventional fuel assemblies. The system envisaged by Babcock and Wilcox is several units that would be combined into a power station of any size, most likely two–four units at a combined 360–720MW using 250MWe turbine generators, also shipped as complete modules.

According to the World Nuclear Association, there are a further 10 SMRs whose development is well advanced, all but one of which is either US, Russian, Chinese or South Korean. Could the UK join the list?

Urenco: small is beautiful
Urenco, best known as a nuclear fuel company operating uranium enrichment plants, is aiming to do just that. The Buckinghamshire-based firm’s CEO, Helmut Engelbrecht, is said to be particularly worried nuclear reactors have become too large and has committed funds to develop what is known as the U-Battery’. In 2008, Urenco gave funding to two universities, the University of Manchester, UK, and the University of Delft, the Netherlands, to conceptualise a design for a uranium battery that would fit on the back of a lorry and produce not just electricity but also heat.

The initial conceptual design for a 1.8m diameter, 4MWe/10MWth reactor was completed in 2012. Unlike established water-cooled reactors, the U-Battery is a gascooled graphite-moderated reactor. Operating seven advanced gas-cooled reactors (AGRs), the UK has extensive knowledge in this area. However, the U-Battery bears little resemblance to the AGR. It is more akin to the pebble bed modular reactor, a tried, tested, yet ultimately failed design developed by Siemens of Germany. The prismatic reactor core comprises thousands of micro-fuel particles, SiC ceramic-coated uranium spheres known as TRISO (tristructural-isotropic), embedded in the graphite matrix.

The spheres, known as pebbles, are cooled by an inert or semi-inert gas, such as helium and nitrogen. The U-Battery would make use of a secondary gas circuit to drive the turbine to produce electricity – a large industrial consumer could deploy the battery as a direct source of process heat as well as embedded power generation.

High temperature gas-cooled reactors typically operate at temperatures of up to 1,000°C. The University of Manchester’s School of Materials is working on new TRISO-coated particle fuels with even greater temperature resistance, and trying to understand materials that could allow the reactor to produce even higher gas outlet temperatures. This could make the heat that it produces useful for a range of industrial processes – including generating hydrogen – as well as just generating electricity. Another advantage of this reactor type is its passive safety, which Urenco claims removes the need for redundant, active safety systems. Because the reactor is designed to handle high temperatures, it can cool by natural circulation and still survive in accident scenarios, Urenco says.

Refuelling, expected to be be required every five years, would mean replacing fuel cartridges that would then be sent to an established spent fuel facility. Urenco is also exploring offering a twin-unit, 8MWe/20MWth U-Battery, which would allow for refuelling in stages.

The next step is to finalise the design and build a prototype, says Paul Harding, Adviser to the CEO and U-Battery project manager. ‘We have a mature concept, and we’re currently working on a pathway with UK industry partners such as Atkins and Amec to build a prototype in the UK to prove the concept works in reality and confirm a U-Battery could be built at the estimated cost,’ he says.

Ah yes, the cost. What is that? ‘We should be able to deliver electricity and heat probably a little bit below current strike price for EDF’s Hinkley Point C [£92.50/ MWh] for the first few U-batteries. By the time we’ve delivered eight–10 units, we should be able to deliver electricity that has a good chance of competing with other packaged power sources. We believe we will beat £79/MWh and be competitive with large nuclear reactors. The real target is to be competitive with alternative embedded generation, such as CHP gas and diesel plants,’ says Harding. Moving from concept through the design phases, to the manufacture and installation of an operational prototype will take eight years, says Harding. A full-size U-Battery prototype, therefore, would not be operational until 2022 at the earliest.

Safety and security concerns
Unlike most other SMRs, which are designed to form part of a larger whole, Urenco characterises its SMR design as a source of microgeneration and envisages the U-Battery to be deployed in remote locations, similar to wind farms. The vision is for it not to require continuous manning, thereby lowering costs, says Harding, as the U-Battery is such that it is inherently safe. ‘If it starts to go outside its operating envelope, it automatically shuts down,’ he says. ‘The fuel is incapable of meltdown under normal emergency accident scenarios, so there will be no need for an emergency evacuation zone. This would fit in an area the size of two squash courts.

But will this appease the regulator, which, under current methodology, would have to treat SMRs as any other nuclear reactor? ‘There will be some interesting discussions as we go through licensing’, says Harding. ‘But we will be proposing to the regulator that the U-Battery would not require the sort of manning levels required by a conventional large nuclear reactor, it may only require one or two people’.

Manufacturing and finance questions
Although Urenco is coming to the end of its current programme for the building of centrifuges that enrich uranium for use in nuclear reactors, it does not expect to manufacture U-Batteries. The likelihood is that Urenco will engage with other UK manufacturers, and it is currently in discussion with research institutions such as the Advanced Manufacturing Research Centre (AMRC) in Rotherham. ‘There will be a consortium, probably called U-Battery Limited,’ says Harding. ‘We have been talking to Rolls-Royce, but they are not ready to come in yet.’

Urenco would like to build the prototype in the UK and, despite the firm’s multinational ownership (it is jointly owned by the Dutch and British Governments, as well as by German utilities firms RWE and E.ON) Harding believes the project has the potential to be all-UK intellectual property.

While the technology and components are proven, the intellectual property is in the particular assembly of the components in a U-Battery configuration. The small size and proposition for factory-based modular manufacturing of a TRISO fuelbased reactor with inert gas coolant and assembly on site is novel. In common with other SMR developers, Urenco believes there is a possibility of hosting the prototype at decommissioned Magnox reactor sites not designated for new nuclear builds. Other suitable sites include Urenco’s facility in Capenhurst, Cheshire.

A nuclear reactor project like the U-Battery is very high risk in terms of return on investment. To lower the risk for investors, Urenco will seek for the Government to provide cornerstone funding to match investment from private sources. Harding says the Technology Strategy Board (TSB) could contribute as much as £1.5m, but this will be some way short of the £130m Urenco’s initial assessment suggests will be required to get to the stage of having an operational prototype.

Urenco’s initial application to the TSB was rejected, but Harding says it will try again to receive the TSB’s Energy Catalyst funding. It will also seek to apply to the European Union’s €80bln Horizon 2020 research and innovation programme. ‘£130m sounds a lot,’ he says, ‘but it is less than others such as Babcock and Wilcox have spent on its mPower SMR programme – it has spent US$500m [£300m], without having been deployed. £20–£40m would get us a long way through the next stages of outline design’.

Steve Kidd, independent nuclear consultant and former Deputy Director General of the World Nuclear Association is sceptical about SMRs. He believes companies like Urenco will struggle to match government funding, as Babock and Wilcox – which announced in April it was cutting back mPower funding to about US$15m per year – found to its cost.
‘The big issue is not capex, but opex – the operation and maintenance costs,’ says Kidd. ‘Unless there is a fundamental change to the regulatory regime, SMRs will still require control rooms, operators, maintenance and all the rigmarole of operating a large nuclear plant. Any gain from capex may be lost from opex for a piddling amount of power compared to large reactors.’

Kidd believes the nuclear industry has come up with the wrong answer to the big question about nuclear – the high cost. ‘Rather than seek a business solution, they have come up with a technical solution to what’s fundamentally an economic problem, or at least a problem in the Western world. Many of these new SMR designs are actually forgotten relics from the 1950s, which were rejected for sound reasons. The industry has got to move on to Generation IV reactors’.